Hazelwick Mill Lane, Crawley

  • TaskDesign and Build

client_logos_17Construction of 12nr Apartments for Sale

Project Summary:

Providence was contracted by Jamesland Homes to provide twelve new build apartments on the outskirts of Crawley.

The project had the benefit of outline planning permission, Providence worked with the Architect Clagues LLP to submit a scheme for full planning permission.

The work consisted of the creation of twelve units, split between two blocks, over three floors. Traditionally built brick and block construction with PCC floors, the elevations were finished with brickwork, featured panels of render and tile hanging.

The site was previously occupied by two houses, which were demolished to make way for the new development. Communal off road car parking was also incorporated onsite due to the adjacent school.

The site was completed within 12 months and occupied within 2 weeks of handover.

Key Project Facts:

Project Value: £1,198,000
Project Period: 12 Months

Project Team:

Client: Jamesland Homes
Employers Agent:

Architect: Clagues LLP
Structural Engineer: BSF Engineering
Building Control: Mid Sussex Building Control
Code/ SAP Assessor: LABC